Various activities and works executed during the last quarter are as follows:
NOTICE: FROM PRESIDENT GREATER MOHALI SOCIETY 1. GBM of JVTY Greater Mohali Apartment Owner’s Association will be held on 18 Oct 2014 at Community Centre-I at the project Site. 2. All allottees are requested to contact, Society for further details. The e-mail address of the society is presidentjvtymohali@gmail.com.
1. Consequent to the visit of DG, AFNHB and Principal Director (Wks) to the project on 01 & 02 Feb 14, a technical audit with the members from AFNHB, Project Staff, Contractor and tile manufacture was carried out from 04 Feb 14 to 16 Feb 14. The aim of the audit was to ascertain the requirement and identify the flats which have shade variation on the floor tiles. The team visited each and every flat except those found locked (Handed Over) in the 18 towers which have been offered to the allottees for taking over. 2. The comprehensive audit report has then been compiled and the total quantity of tile requirement ascertained. The required quantity has been intimated to the tile manufacturer i.e. M/s. Somany Tiles. 3. M/s. Somany has been instructed to carry out a thorough check of all its stocks which were supplied with similar shades, during the corresponding period when the tiles were supplied to Mohali project. Although few boxes have been located at Ahmadabad, these are very less compared to our requirement. M/s. Somany has sought one weeks� time i.e. upto 04 Mar 14 to carryout full search on all over India basis with their stockiest to locate similar shade tiles if available. Based on the total tiles located, these would then be brought to the Mohali Project and replacement in those flats where shade variations exists will be under taken. At the same time allottees are at liberty to locate matching tiles from the market (including other manufactures) and the tiles will be replaced. 4. Next update would be posted after 07 Mar 14 to appraise the status.