PROJECT UPDATE AS ON 31 JUL 09
MEERUT PROJECT
  • Boundary wall upto plinth level executed through MDA.
  • Land Registration in final stages ( likely by 10 Aug 09).
  • Scheme open for registration upto 31 Aug 09.
  • Architect Selected.
  • Contractor selection in progress.
  • Plans finalised and ready for submission to Meerut Development Authority post registration of land.

NEW TOWN KOLKATA PROJECT

  • 70% structure work complete.
  • Construction of Car parking and finishing works is in progress.
  • Majority allottees did not opt for changes having financial effect post completion of sample flats hence, changes not being implemented.
  • 8th installment due on 07 Nov 09.
  • Latest site photographs uploaded.

COIMBATORE PROJECT

  • Plans at final stages of Approval with District Town & Country Planning Department, Chennai.
  • Technical Bid received from 9 contractors.
  • Construction likely to commence Nov 09.

BHUBNESHWAR PROJECT

  • 4 Acres of land in Chandershekharpur adjacent to AWHO project allotted by Government. Lease Deed execution in process.
  • Executive Committee (Works) planned on 27 Aug 09 for selection of Architect.
  • Scheme likely to be opened in Oct 09 for Demand Survey registrants.

BANGALORE PHASE III PROJECT

  • Foundation work of all blocks completed.
  • Casting of Slabs is in progress.
  • Sample flat completion expected Nov 09.
  • 4th installment due on 07 Aug 09.

GREATER MOHALI PROJECT

  • Basement work for parking completed.
  • Foundation work of all buildings completed.
  • Slab of approximately 400 flats completed.
  • Internal finishing works in progress.
  • Sample flat meeting for Officers flats was held with allottees on 04/05 Jun 09. Minutes on suggestions shall be circulated by end Aug 09.
  • PDC Is Dec 2010.
  • 7th installment due on 08 Sep 09.
  • Sample Flat photographs uploaded.

DEHRADUN PROJECT.

  • Architect selected.
  • Contractor Selection in progress.
  • Technical Bid received from 8 contractors.
  • Commercial Bid shall be issued by end Aug 09.
  • NOC from Environment and Pollution Control Board and plan sanction from Mussorie, Dehradun Development Authority is in process.
  • Land conversion to Residential use is in final stages.
  • First instalment due on 08 Dec 09.

KANDAGHAT PROJECT

  • 90% Structure work completed.
  • Finishing work in progress.
  • Draw of lots and Society formation Scheduled at 1000 Hrs on 19 Sep 09 at Examination Hall, Air Force Station, Race Course, New Delhi-3.
  • Choices for stilt/open parking sought from allottees last date for receiving choices 27 Aug 09.

HYDERABAD PROJECT

  • 70% Structure work completed.
  • Finishing work in progress.
  • Sample flat meeting with allottees held on 08/09 Jun 09. Meeting on suggestions shall be Sent by end Aug 09.
  • PDC is Jun 10.
  • 6th installment due on 21 Aug 09.
  • Sample Flat photographs uploaded.

GREATER NOIDA PROJECT.

  • Construction of foundation work in progress.
  • Draw of Lots for allotment held on 04 Jul 09.
  • Allotment letters issued on 04 Aug 09. refund of unsuccessful registrants in process are under dispatch.
  • Ist installment is due on 15 Sep 09.