CURRENT CONSTRUCTION STATUS OF THE ONGOING SCHEMES
Greater Mohali Project.
  • 70% structure work complete.
  • Finishing works is in progress.
  • Minutes of sample flat meeting circulated option from allottees on additional costs sought by 25 Feb 10.
  • Lift contract finalised with M/s. Thysson Krupp.
  • Photographs as on Jan 2010.uploaded.
  • Next Installment due as per following details.
  • CATEGORY
    INSTALMENTS
    DATE
    A-I
    3.03 Lacs
    08 April 2010
    A-II
    2.38 Lacs
    08 April 2010
    A-III
    1.92 Lacs
    08 April 2010
    B
    1.50 Lacs
    08 April 2010
  • Kandaghat
    • 100% structure work complete.
    • Finishing work is in progress.
    • Common facilities are to be taken over by Society prior to commencing handing over of dwelling units.
    • Handing over schedule shall be promulgated shortly.
    • Final installment likely to be called on March 2010.
    • Photographs as on Jan 2010 uploaded.
    Hyderabad Phase - III
    • 90% structure work complete.
    • Finishing work is in progress.
    • Suggestion incorporated as per allottees suggestions for sample flat meeting.
    • Construction of Community Center and Swimming Pool in progress.
    • Photographs as on Jan 2010 uploaded.
    • Next Installment due as per following details.
  • CATEGORY
    INSTALMENTS
    DATE
    A-I
    4.10 Lacs
    20 April 2010
    A-II
    3.75 Lacs
    20 April 2010
    B
    1.90 Lacs
    20 April 2010
  • New Town Kolkata
    • 90% structure work complete.
    • Community Centre work commenced.
    • Finishing work and external development work in progress.
    • Efforts on to obtain timely power supply for the complex.
    • Draw of lots for specific flat numbers likely by April 2010.
    • Photographs as on Jan 2010 uploaded.
    • Choices for parking letter under dispatch.
    • Final call up letter indication VAT/Service Tax charges, increase in price due to cost of cement/steel and balance shall be intimated by May 2010.
    Bangalore Phase – III
    • Sample flats of all categories ready, photographs uploaded.
    • Allottees meeting held on 21/22 Jan 2010. Minutes shall be circulated shortly.
    • Plans for Community Facilities and external electrification being submitted to local authorities for approval.
    • Photographs as on Jan 2010 uploaded.
    • Next Installment due as per following details.
  • CATEGORY
    INSTALMENTS
    DATE
    A- I
    4.85 Lacs
    09 March 2010
    A- II
    4.15 Lacs
    09 March 2010
    A- III
    3.25 Lacs
    09 March 2010
    B
    2.35 Lacs
    09 March 2010
  • Greater Noida
    • Structure at 3rd floor level.
    • Sample flat likely to be completed by end March 2010.
    • Next installment of Rs. 8 Lacs due on 09 April 2010
    • Photographs as on Jan 2010 uploaded.
    Dehradun Phase–II
    • Chief Minister cleared the land conversion to residential use in Oct 09. Final notification awaited.
    • Contractor selection in final stages.
    • Construction likely to commence from April 2010.
    • Next Installment due as per following details.
  • CATEGORY
    INSTALMENTS
    DATE
    A-I
    4.25 Lacs
    05 March 2010
    A-II
    3.50 Lacs
    05 March 2010
    B-I
    2.70 Lacs
    05 March 2010
    B-II
    2.10 Lacs
    05 March 2010
  • Coimbatore
    • Plans cleared from District Town and Country Planning Department, Chennai, but not yet released from Corporation of Coimbatore.
    • Deposits for Development Charges/Infrastructure Charges amounting approximately Rs. 1.2 crore paid to Local Planning Authority, Coimbatore.
    • Construction likely to commence from April 2010.
    Meerut
    • Possession of land obtained from Meerut Development Authority.
    • Conveyance Deed and other related documentation completed.
    • Boundary wall completed upto plinth level. Plans approved by Meerut Development Authority.
    • Aviation clearance awaited. Tenders and drawings prepared. Contractors short listing completed.
    • Work expected to commence by April 2010. No major hurdles as on date.
    • Scheme open on first come first serve basis.
    • Next Installment due as per following details.
  • CATEGORY
    INSTALMENTS
    DATE
    A-I
    3.30 Lacs
    09 March 2010
    A-II
    2.85 Lacs
    09 March 2010
    B-I
    1.98 Lacs
    09 March 2010
    B-II
    1.54 Lacs
    09 March 2010
  • Bhubneshwar
    • 4 acres of land in Chander Shekharpur adjacent to AWHO project allotted by Government.
    • Lease Deed executed.
    • Physical possession obtained.
    • Architect selected.
    • Plans under finalisation.
    • Scheme likely to be launched by April 2010.
    9.2.2010