CURRENT CONSTRUCTION STATUS OF THE ONGOING SCHEMES |
Greater Mohali Project.
- 70% structure work complete.
- Finishing works is in progress.
- Minutes of sample flat meeting circulated option from allottees on additional costs sought by 25 Feb 10.
- Lift contract finalised with M/s. Thysson Krupp.
- Photographs as on Jan 2010.uploaded.
- Next Installment due as per following details.
CATEGORY |
INSTALMENTS |
DATE |
A-I |
3.03 Lacs |
08 April 2010 |
A-II |
2.38 Lacs |
08 April 2010 |
A-III |
1.92 Lacs |
08 April 2010 |
B |
1.50 Lacs |
08 April 2010 |
|
Kandaghat
- 100% structure work complete.
- Finishing work is in progress.
- Common facilities are to be taken over by Society prior to commencing handing over of dwelling units.
- Handing over schedule shall be promulgated shortly.
- Final installment likely to be called on March 2010.
- Photographs as on Jan 2010 uploaded.
|
Hyderabad Phase - III
- 90% structure work complete.
- Finishing work is in progress.
- Suggestion incorporated as per allottees suggestions for sample flat meeting.
- Construction of Community Center and Swimming Pool in progress.
- Photographs as on Jan 2010 uploaded.
- Next Installment due as per following details.
CATEGORY |
INSTALMENTS |
DATE |
A-I |
4.10 Lacs |
20 April 2010 |
A-II |
3.75 Lacs |
20 April 2010 |
B |
1.90 Lacs |
20 April 2010 |
|
New Town Kolkata
- 90% structure work complete.
- Community Centre work commenced.
- Finishing work and external development work in progress.
- Efforts on to obtain timely power supply for the complex.
- Draw of lots for specific flat numbers likely by April 2010.
- Photographs as on Jan 2010 uploaded.
- Choices for parking letter under dispatch.
- Final call up letter indication VAT/Service Tax charges, increase in price due to cost of cement/steel and balance shall be intimated by May 2010.
|
Bangalore Phase – III
- Sample flats of all categories ready, photographs uploaded.
- Allottees meeting held on 21/22 Jan 2010. Minutes shall be circulated shortly.
- Plans for Community Facilities and external electrification being submitted to local authorities for approval.
- Photographs as on Jan 2010 uploaded.
- Next Installment due as per following details.
CATEGORY |
INSTALMENTS |
DATE |
A- I |
4.85 Lacs |
09 March 2010 |
A- II |
4.15 Lacs |
09 March 2010 |
A- III |
3.25 Lacs |
09 March 2010 |
B |
2.35 Lacs |
09 March 2010 |
|
Greater Noida
- Structure at 3rd floor level.
- Sample flat likely to be completed by end March 2010.
- Next installment of Rs. 8 Lacs due on 09 April 2010
- Photographs as on Jan 2010 uploaded.
|
Dehradun Phase–II
- Chief Minister cleared the land conversion to residential use in Oct 09. Final notification awaited.
- Contractor selection in final stages.
- Construction likely to commence from April 2010.
- Next Installment due as per following details.
CATEGORY |
INSTALMENTS |
DATE |
A-I |
4.25 Lacs |
05 March 2010 |
A-II |
3.50 Lacs |
05 March 2010 |
B-I |
2.70 Lacs |
05 March 2010 |
B-II |
2.10 Lacs |
05 March 2010 |
|
Coimbatore
- Plans cleared from District Town and Country Planning Department, Chennai, but not yet released from Corporation of Coimbatore.
- Deposits for Development Charges/Infrastructure Charges amounting approximately Rs. 1.2 crore paid to Local Planning Authority, Coimbatore.
- Construction likely to commence from April 2010.
|
Meerut
- Possession of land obtained from Meerut Development Authority.
- Conveyance Deed and other related documentation completed.
- Boundary wall completed upto plinth level. Plans approved by Meerut Development Authority.
- Aviation clearance awaited. Tenders and drawings prepared. Contractors short listing completed.
- Work expected to commence by April 2010. No major hurdles as on date.
- Scheme open on first come first serve basis.
- Next Installment due as per following details.
CATEGORY |
INSTALMENTS |
DATE |
A-I |
3.30 Lacs |
09 March 2010 |
A-II |
2.85 Lacs |
09 March 2010 |
B-I |
1.98 Lacs |
09 March 2010 |
B-II |
1.54 Lacs |
09 March 2010 |
|
Bhubneshwar
- 4 acres of land in Chander Shekharpur adjacent to AWHO project allotted by Government.
- Lease Deed executed.
- Physical possession obtained.
- Architect selected.
- Plans under finalisation.
- Scheme likely to be launched by April 2010.
|
|
9.2.2010 |