CURRENT CONSTRUCTION STATUS OF THE ONGOING SCHEMES( MAY 2010)

Greater Mohali.

  • 85% structure work complete.
  • Finishing works is in progress.
  • Suggestion post completion of Sample Flat being implemented as per majority choice.
  • Lift contract finalised with M/s. Thysson Krupp.
  • Photographs as on May 2010.uploaded.
  • Efforts on to obtain external electrical sanction of the scheme at the earliest.
  • Draw of lots for specific flats tentatively scheduled in Nov 10.
  • Choice for flats with additional areas and type of parking shall be sought by Jun 10.
  • Next Installment due as per following details.

    CATEGORY
    INSTALLMENTS
    DATE
    A-I
    3.04 Lacs
    03 Sep 10
    A-II
    2.42 Lacs
    03 Sep 10
    A-III
    1.92 Lacs
    03 Sep 10
    B-I
    1.54 Lacs
    03 Sep 10

    PDC – 12 Blocks, Feb 11, Balance- Mar 11.

    Kandaghat.

  • 100% structure work complete.
  • Finishing work is in progress.
  • Common facilities have been taken over by Society. Few facilities are yet to be taken over by Society.
  • Handing over of DUs commenced from 14 May 10.
  • Photographs as on May 2010 uploaded. DG, AFNHB inaugurated the project on 13 May 10.
  • Water available through tankers till permanent water connection is through.

    Hyderabad Phase – III.

    98% structure work complete.
    Finishing work is in progress.
    Allottees suggestions during sample flat meeting incorporated.
    Construction of Community Center and Swimming Pool in progress.
    Photographs as on May 2010 uploaded.
    Draw of lots For flat Numbers and Parkings is scheduled on 26-27 Jun 10 at project site.
    Next Installment due as per following details.
    CATEGORY
    INSTALLMENTS
    DATE
    A-I
    4.10 Lacs
    03 Aug 10
    A-II
    3.75 Lacs
    03 Aug 10
    B-I
    1.90 Lacs
    03 Aug 10

    New Town Kolkata.

    Structure work complete.
    Community Centre / Swimming Pool work in progress.
    Finishing work and external development work in progress.
    Efforts on to obtain timely power supply for the complex.
    Draw of lots for specific flat numbers, Parking and formation of Residents Welfare Association scheduled on 12/13 June 2010 at project site.
    Photographs as on May 2010 uploaded.
    PDC – Sept 10.

    Bangalore Phase – III.
    Three building at 11th Floor level and balance three at 7th floor level.
    Suggestions post completion of Sample flats implemented as per majority choice.
    Plans for Community Facilities and External Electrification submitted to local authorities for approval.
    Photographs as on ¬¬ May 2010 uploaded.
    Next Installment due as per following details.
    CATEGORY
    INSTALLMENTS
    DATE
    A-I
    4.85 Lacs
    06 Sep 10
    A-II
    4.15 Lacs
    06 Sep 10
    A-III
    3.25 Lacs
    06 Sep 10
    B-I
    2.35 Lacs
    06 Sep 10

    PDC – Feb 11.

    Greater Noida.
    Structure at 7th floor level.
    Sample flat opened on 22 Apr 10 and appreciated by all allottees.
    Few suggestions have been received which shall be implemented at additional cost after majority consent of allottees. Options are being sought shortly.
    Next installment of Rs. 8 Lacs due on 09 Jul 10.
    Photographs of sample flat uploaded.
    PDC – Mar 11.

    Dehradun Phase – II.
    Chief Minister cleared the land conversion to residential use in Oct 09.
    Plan approvals expected & construction likely to commence from June 10. Contract awarded to M/s. NG Constructions & M/s. Umaxe.
    Excavation work commenced on 08 May 10.
    Bhoomi Pujan Ceremony was held on 16 May 10 on the day of Akshay Tritiya. Photographs uploaded on website.
    Next Installment due as per following details.
    CATEGORY
    INSTALLMENTS
    DATE
    A-I
    4.25 Lacs
    05 Jul 10
    A-II
    3.50 Lacs
    05 Jul 10
    B-I
    2.70 Lacs
    05 Jul 10
    B-II
    2.10 Lacs
    05 Jul 10

    Coimbatore.

    Plans approved by Corporation of Coimbatore on 16 April 2010.
    Deposits for Development Charges/Infrastructure Charges amounting to approximately Rs. 1.2 crore paid to Local Planning Authority, Coimbatore.
    M/s. Shapoorji Pallonji selected as contractor.
    Bhoomi Puja planned on 27 May 2010 at site between 1000 Hrs to 1100 Hrs. All allottees invited.
    Revised cost based on L1 bid and instalment schedule shall be intimated to allottees by early June 2010.
    PDC – May 12

    Meerut.
    Bhoomi Pujan Ceremony was held on 17 May 10 and work commenced on ground.
    Photographs of Bhoomi Pujan uploaded.
    Conveyance Deed and other related documentation completed.
    Boundary wall completed upto plinth level. Plans approved by Meerut Development Authority.
    Work commenced. Contract awarded to M/s. Omax.
    Scheme still open on first come first serve basis for few vacancies in Phase-I.
    Installment schedule shall be intimated by Jun 10.

    PDC – May 12
    Bhubneshwar.

  • Plans have been finalized and are being submitted to Bhubaneswar Development Authority by end May for approval. The approvals are likely to take four months.
  • Boundary wall work commencing from 01 Jun 10.
  • Scheme likely to be opened for registration for demand survey allottees only by end Jul 10.
  • Efforts are on to acquire additional land at Chandaka / Mendhasala / Paikarpur RI Circles for Phase II.
  • As per the policy of the Board, work on ground will commence only after obtaining all approvals from Competent Authorities.