MEERUT
Shatabdi Nagar, Sector 4B, Po. Partapur, Meerut. Adjacent to Ansals Panchvati Enclave.
Status: (26 Sep 14)
WEB UPDATE 26 SEP 2014
    AFNHB MEERUT PROJECT
    1. In the past few weeks, the progress on the site has suffered due to inadequate resources and inadequate man power deployed by contractor. The contractor has been citing financial crunch.
    2. Consequently, the Board had issued the Show Cause notice to the contractor and warned to cancel the contract and carry out the work by third agency at his risk and cost.
    3. However, recently the civil contractor has approached the Board seeking mobilization advance against Bank Guarantees in order to infuse funds in the project and achieve the desired progress. The Board has facilitated this and we expect the work to pick up and progress satisfactorily. The Board in order to safeguard the allottees interest had been insisting for the BGBs so that allottees interests are not compromised. The advance will carry the necessary interest which will be ploughed to the Project by the Board. The Board will take the final decision by 15 Oct 14 and intimate the allottees.
    4. Please be assured that the board will not spare any efforts at closely monitoring the work and ensuring that work progress at brisk pace to make up for lost time.
No penal rate of interest by AFGIS for Projects construction in progress. (10 Oct 2014). [Read more....]
Waiver of Penal Rate of Interest on HBL due to revision of date of completion of AFNHB Schemes (31 Jul 14 ): read more ...
Revised date of Second Additional Instalment from 30 Sep 14 to 28 Nov 14 : Letter dated (30 Jul 14 ): read more ...
  • UPDATE MEERUT AFNHB PROJECT-23 JUL 14.[Read more...]
  • Regional Rapid Transit System (RRTS) from Delhi to Meerut (14 Jun 14). [Read more...]
  • Postpone of first additional Instalment from 30 Apr 14 to 16 Jun 14. read more...
  • Revised Instalment Schedule (10 Dec 13). read more...
  • Delhi Meerut Express Way Update (22 Nov 13). read more...
  • Last installment further postponed from 07 Aug 13 to 05 Dec 13 : Letter dated 17 Jul 13. more...
  • Last installment further postponed from 07 May 13 to 7 Aug 13 : Letter dated 02 Apr 13. more...
  • Last installment further postponed from 07 Jan 13 to 7 May 13:Letter dated 23 Nov 12. more...
  • Allottees Suggestions : Letter dated 09 Aug 12. more...
  • Registration Re-opened for AI and AII Category for Priority I to IV for few vacancies. Last date of Regn.15 Sep 12. more...
  • Draw result held on 23 Jul 12. more...
  • 8th Installment Postponed from 13 Aug 12 to 07 Jan 13 : Letter dated 05 Jul 12 more...
  • Registration extended from 30 Jun 12 to 7 Jul 12. more...
  • Additional covered parking for A-I Category : (18 Jun 12) more...
  • Meerut and Jaipur Ph-II Schemes Re-opened for Priority I to IV for few vacancies. Last date of Regn.30 Jun 12. more... (25 May 12)
  • Suggestions of Allottees: (18 Apr 12) more...
  • Sample Flat for AI and AII category were inaugurated on 7th and 8th May 11 and B1and BII category on 11 Jun 2011.
  • Old Updates Bin
    Forwarding of Technical Brochure 2010 : Letter dated 14 Jul 10 more ....
    Master Plan Part-1 :Master Plan Part-2 : Master Plan Part-3 :Master Plan Part-4 : Master Plan Part-5
    TENTATIVE COST , AREA, ACCOMMODATION ENUMERATED BELOW:
    TYPE
    SUPER AREA (APPROX) IN SQ FT
    TENTATIVE COST (RS.IN LAKH )
    REGN. AMOUNT (IN RUPEES)

    ACCOMODATION

    OFFICERS :

    AI
    1630
    27.99/25.98
    1,01,000/-
    DRAWING/DINING, THREE BEDROOMS, THREE TOILETS, BALCONIES & KITCHEN
    AII
    1450
    24.81/23.11
    1,01,000/-

    DRAWING/DINING, THREE BEDROOMS, TWO TOILETS, BALCONIES & KITCHEN

    AIRMEN / SAILORS
    B-I
    1010
    16.10
    51,000/-
    DRAWING / DINING TWO BEDROOMS, TWO TOILETS, KITCHEN AND BALCONIES
    B-II
    810
    12.90
    51,000/-
    DRAWING/DINING, TWO BEDROOMS, TWO TOILETS, KITCHEN AND BALCONIES
     

    - PARKING, SERVICE TAX, VAT AND LONG TERM MAINTENANCE CHARGES EXTRA.
    - THE NUMBER OF DWELLING UNITS FOR EACH TYPE SHALL BE BASED ON ACTUAL DEMAND.

    FOR FURTHER DETAILS CONTACT (011) 2379 3462/3463/2881. E-Mail Address:directorgeneral@afnhb.org

    Instalment Plan:(MRA, MRB, MRC and MRD)
    AI
    AII
    BI
    BII
    Due Date
    Regn
    1,01,000
    1,01,000
    51,000
    51,000
    31 Aug 09
    First
    3,30,000
    2,85,000
    1,98,000
    1,54,000
    08 Dec 09
    Second
    3,30,000
    2,85,000
    1,98,000
    1,54,000
    09 Mar 10
    Third
    3,30,000
    2,85,000
    1,98,000
    1,54,000
    08 Oct 10
    Fourth
    3,30,000
    2,85,000
    1,98,000
    1,54,000
    10 Dec 10
    Fifth
    3,30,000
    2,85,000
    1,98,000
    1,54,000
    11 Mar 11
    Sixth
    3,30,000
    2,85,000
    1,98,000
    1,54,000
    11 Aug 11
    Seventh
    3,30,000
    2,85,000
    1,98,000
    1,54,000
    13 Feb 12
    Eighth
    1,88,000
    2,16,000
    1,74,000
    1,62,000
    05 Dec 13
    Ninth
    2,66,672
    2,63,982
    2,03,792
    1,95,012
    16 Jun 14
    Tenth (Tentative)
    3,80,000
    3,80,000
    3,80,000
    3,80,000
    28 Nov 14
    Balance plus LTMF/ Service Tax/ VAT/ Parking shall be intimated later depending on actual prior to handing over of the dwelling units.
    Instalment Plan:(MRE & MRF)
    A-I
    A-II
    Due Date
    Regn
    1,01,000
    1,01,000
    09 Jun 11
    First
    6,00,000
    5,00,000
    10 Jun 11
    Second
    6,00,000
    5,00,000
    09 Sep 11
    Third
    6,00,000
    5,00,000
    10 Jan 12
    Fourth
    6,00,000
    5,00,000
    30 Apr 12
    Fifth
    2,98,000
    3,81,000
    05 Dec 13
    Sixth
    2,66,672
    2,63,982
    16 Jun 14
    Seventh (Tentative)
    3,80,000
    3,80,000
    28 Nov 14
    Balance plus LTMF/ Service Tax/ VAT/ Parking shall be intimated later depending on actual prior to handing over of the dwelling units.
    Photos, News, Master Brochure etc.
    Inaguration
    3D View
    Plan AI
    Plan AII
    Plan BI
    Plan BII

    Sample Flat A-II
















    Prog. 1 Dec 13




















    Prog.22 Dec 13




























    Prog,1 Jan 14

















    Prog,1 Feb 14




















    Prog 24 Mar 14



























    Prog. 7 Apr 14








    Prog. 1 May 14













    Prog. 1 Jun 14






















    RRTS

    Prog. 1 Jul 14











    Prog. 1 Aug 14
















    Updates. 28 Aug 14
    Updates. 28 Aug 14