DEHRADUN (PREM NAGAR)
Village Jajhar, 04 Km from IMA on Chakrata Road.
Status:(6 May 14)
1. Reference is made to a few queries of allottees regarding handing over of dwelling units for project at Prem Nagar Dehradun Phase-II project.
2. As you are aware during the monsoons of 2013 the basements were flooded with catchment water as the covering of open areas were still being executed. This had resulted into complete halt in the construction activities in the basement and substructure. Also, the services have been adversely affected and the work for services like storm water drains, sewerage and STP (located in the basements) were delayed.
3. Further the final decision from UPCL for granting the available electrical supply for the project is awaited and lines for the same are being laid. Due to this even after advance stage of completion of external electrification work in the project, energisation is still awaited. However, rigorous follow up is being undertaken by this Board to ensure the said availability at earliest.
4. It may be appreciated that it will not be prudent on our behalf to offer the towers (already in the stage of handing over individually) without provisioning for basic services to be provided for residing in the premises.
5. In view of the above the completion of project fit for occupation and handing over is likely to be delayed to Oct/Nov 14. The Draw of Lots is also deferred accordingly.
6. Further development in this context will be promulgated through the AFNHB website.
  • Deferrment of Ad-hoc Installment from 03 Sep 13 to 04 Oct 13 : letter dt. 19 Aug 13. Read more ...
  • Reason and Justification of Instalment Schedule on 03 Sep 13. (12 Aug 13) more...
  • Ad-hoc Installment due on 03 Sep 13 : dt. 23 Jul 13. Read more ...
  • Exterior colour scheme Option (Closed on 12 Mar 13). more...
  • 1. This is to bring to the notice of all Allottees of AFNHB Dehradun Phase-II Project that despite the site location in the vicinity of River Tons the most devastating floods ever in Uttarakhand has had no adverse effect on the Buildings and Structures of Dehradun Project. Post construction of underground Double Basements, Retention Walls and completion of all Structures Project has not experienced any negative impact of flood/ damages by River Tons.
  • 2. The current photographs are being loaded on the web site for removing all past apprehensions of the allottees.
  • Sample Flat Meeting on 16 Jun 12 for Cat. BI and BII :27 Jun 12.more...
  • Suggestions of Allottees for AI and A-II Category :12 Jun 12.more...
  • Update (Sample flat for Cat B-I & B-II):14 May 12.more...
  • Suggestions of Allottees for A-II Category :11 Apr 12.more...
  • Forwarding of Technical Brochure:28 Mar 12.more...
  • Update:Postponement of 5th and 6th Installment:12 Mar 12.more...
  • Sample Flat Meeting:06 Mar 12.more...
  • Sample Flats of A-II category Inaugurated on 24 Dec 11. (26 Dec 11)
  • Electrical approval obtained from State Electricity Board. (12 Dec 11)
  • Press Release on amended MDDA By-Laws. more...(Uploaded on 2 Dec 11)
  • Revised Schedule of Installment : Letter dated 1 Dec 11. more...
  • Change of date for allottees meeting (Category A-II). more...
  • Old Updates Bin
    TYPE
    SUPER AREA (APPROX) IN SQ FT
    TENTATIVE COST (RS.IN LAKH )
    REGN. AMOUNT (IN RUPEES)

    ACCOMODATION

    OFFICERS :

    AI
    2075
    30.50
    1,01,000/-
    DRAWING/DINING, FOUR BEDROOMS, THREE TOILETS, BALCONIES & KITCHEN
    AII
    1740
    25.60
    1,01,000/-

    DRAWING/DINING, THREE BEDROOMS, THREE TOILETS, BALCONIES & KITCHEN

    AIRMEN / SAILORS
    B-I
    1300
    19.10
    51,000/-
    DRAWING / DINING THREE BEDROOMS, TWO TOILETS, KITCHEN AND BALCONIES
    B-II
    1000
    14.70
    51,000/-
    DRAWING/DINING, TWO BEDROOMS, TWO TOILETS, KITCHEN AND BALCONIES
     

    - PARKING, SERVICE TAX, VAT AND LONG TERM MAINTENANCE CHARGES EXTRA.
    - THE NUMBER OF DWELLING UNITS FOR EACH TYPE SHALL BE BASED ON ACTUAL DEMAND.

    For further details contact (011) 2379 3462/3463/2880. E-mail Address:directorgeneral@afnhb.org

    Instalment Plan :
    AI
    AII
    BI
    BII
    Due Date
    Regn
    1,01,000
    1,01,000
    51,000
    51,000
    06 Feb 09
    First
    4,25,000
    3,50,000
    2,70,000
    2,10,000
    05 Mar 10
    Second
    4,25,000
    3,50,000
    2,70,000
    2,10,000
    10 Sep 10
    Third
    4,25,000
    3,50,000
    2,70,000
    2,10,000
    25 Apr 11
    Fourth
    4,25,000
    3,50,000
    2,70,000
    2,10,000
    05 Oct 11
    Fifth
    4,25,000
    3,50,000
    2,70,000
    2,10,000
    05 Jul 12
    Sixth
    4,25,000
    3,50,000
    2,70,000
    2,10,000
    05 Nov 12
    Ad_hoc
    3,20,000
    3,00,000
    2,68,000
    2,00,000
    04 Oct 13
    Balance plus increase in cost due to Cement and Steel escalation, increase in Tax etc. and LTMF and Parking.
    Location Map and other Photographs
    Key Plant
    3D Model
    Location
    Layout Plan
    AI-Unit Plan
    AII-Unit Plan
    BI-Unit Plan
    BII-Unit Plan

    View of AI
    Aerial View
    Prog.24 May 13







    Prog.20 Jun 13








    Current Pic's










    Prog.7 Aug 13











    Prog. 17 Aug 13



    Prog. 3 Sep 13















    Prog.11 Oct 13



    Prog.6 Nov 13








    Prog.17 Dec 13





    Prog.3 Jan 14




    Prog.16 Jan 14




    Prog.11 Feb 14





    Prog. 3 Mar 14




    Prog. 9 Apr 14




    Prog. 6 May 14