AFNHB/WKS/1542-II 17 Sep 07 To All Allottees of Pune Phase- II UPDATE ON PUNE PHASE II AFNHB PROJECT 1. Please refer our earlier letter of even number dated 04 Jun 07. 2 A user committee meeting was held at site on 30 Jul 07, post completion of the sample flat. Following were suggested and discussed by allottees present: -
3. The progress of the project is satisfactory and as on date 80% of the structural work has been completed. The work on plumbing, masonry, internal and external plastering is in progress. The draw of lots for specific flat numbers shall be held in Feb 08, the exact date of which shall be communicated separately. 4. On allottees request, the works at Para 2 (b) and 2 (f) are being executed at a additional cost of Rs 2050/- per flat.
| ||||
|
|